L&T alleges that the project was delayed mainly due to Telangana government dillydallying over the change in the alignment of the project and failing to provide the right of way at various stretches which delayed the work for about a year.
L&T has written to the Telangana government that it should bear the 4000 Plus Crores of additional burden. Earlier the concessionaire has given indications that it may quit the project if its demands are not met with. Telangana government can not afford that since it will send bad signals to the investors.