The approved PPAs will later be submitted to the Power Grid Corporation along with the application for allotment of grid corridor. However the is no available Grid corridor for the use of Telangana. All the existing lines are already booked by Tamil Nadu government. To bring Chhattisgarh power to Telangana, fresh lines had to be laid between Wardha and Dichpally and this process will approximately roughly 18 months.
According to the experts, it will take at least three years to enjoy the benefits of 1000 MW supply. They say it will take 27 months for completion of works once the contract works are complete.