The Bhoomi Puja for Assembly will be held on July 20th and High Court Building on August 17th. According to the plan now the G+3 Assembly building construction will cost 245 Crore and is expected to be complete by 4th October 2018. High Court building will be constructed as G+4 and will cost 450 Crore.
The Permanent Secretariat Building construction will begin on May 10th and will be complete by December 25th, 2018. These buildings will come up on 900 acres. If they are completed as per the plan now, they will remain as testimony for Naidu in 2019 election.