The Concessionaire has been asking for the extension of project schedule by 18 months for the past one year. L&T alleged that the delay is due to the government failing to give the Right of Way as per the original schedule.
L&T has been asking for extension of project schedule by 18 months for the past one year. But then the Telangana government is not moving the things and has only appointed an independent engineer to look into these issues. The project developer is going to opt for arbitration but such move will be defaming for Telangana government.