But then purchasing power at a higher cost from private producers and the delay in construction of thermal power plants would result in cost escalation and the additional expenditure will have to be borne by the consumers. Poor Planning before taking up Thermal Power Plants has resulted in this mess, Power Experts say.
Bhadradri power plant, a 4×270 thermal power plant at Manu-guru has been also delayed and may be commissioned by December 2017 or early 2018, provided the environmental committee gives its approval by November end. On the other side, Telangana is hoping that Wardha-Dichpalli-Maheshwaram 765 KV transmission line is likely to be completed by January next and will ensure Telangana procure electricity from Chhattisgarh.