Numerous Roadblocks for Vijayawada Metro

Amaravati Metro Rail Corporation (AMRC) had decided to cancel the tenders called for the project as they could not be finalized in the designated time. The project had already been delayed because of lack of funding as well as the delay in the land acquisition. Furthermore, the state government is yet to sign an MOU with Delhi Metro Rail Corporation to bring it on board as a concessionaire.

[m9ad]

ADVERTISEMENT

The Central government also has its own share of troubles regarding the project. The Central government did not issue the necessary permissions for the project to finalize the tenders. And then JICA is yet to finalize the loans it has committed for the project. The state government earlier this month allocated 100 Crore for the land acquisition.

The state government is planning to call for the bids only after the land acquisition is complete and after the agreement is signed with DMRC. The government is planning to take the land via pooling as well as acquisition. Interested parties will be given lands near Amaravati and others will get compensation according to Land Acquisition Act.

Share
Sridhar Raavi

Sridhar is a highly experienced hand in Telugu politics, writing and analyzing political happenings in Andhra Pradesh and Telangana. An IT engineer turned news junkie, Sridhar has a sharp eye for catching news as it u…

Published by

Recent Posts

Telugu Directors: How One Hit Can Change Their Market

A hero can have a bad film and still enter the next one with his…

25 minutes ago

రెండు కేసులలో కదలికలు.. అంటే అర్థం అది కాదు!

రాజకీయ నాయకులపై కేసులంటే అవి అజ్ఞాతవాసంలో పాండవులు జమ్మిచెట్టుపై దాచి ఉంచిన అత్యంత శక్తివంతమైన అస్త్రాల వంటివే. కనుక అధికారంలో…

45 minutes ago