Andhra Pradesh is accelerating work on the Polavaram project, aiming to dedicate its first phase to the nation by June 2027. Chief Minister Chandrababu Naidu has directed officials to complete the main dam by March 2027. However, engineering officials believe they could finish the work by the end of May. The project has entered a crucial construction phase. The diaphragm wall is already complete and work on the main dam is progressing. Only around 10 per cent of the work connecting the reservoir with the right and left main canals remains.
Main Dam Construction Gains Pace:
The main dam comprises two sections. Gap-1 stretches 584 metres while Gap-2 extends nearly 1.7 kilometres. Both sections must reach an elevation of +53.32 metres. Construction involves nearly 100 compacted layers. Engineers test each layer for strength and quality before proceeding with the next. The dam will have soil, rock and sand filter layers. Its base will be approximately 500 metres wide. In Gap-1, construction has reached nearly 33 metres across a 500-metre stretch. Around six lakh cubic metres of work remain out of the total 12.83 lakh cubic metres. Gap-2 has reached a height of 23 metres. Nearly 33 lakh cubic metres of work remain out of the total 61.52 lakh cubic metres.
More Machinery Deployed:
Contractor Megha has arranged 60 additional dumpers and nine excavators to speed up construction. The project requires around 8.75 lakh cubic metres of soil and 49.20 lakh cubic metres of rock. Recent cyclones disrupted work for nearly 10 days. Officials are now focusing on recovering lost time and maintaining the construction schedule. The designs for the Gap-2 clay reach between elevations +25 metres and +53.32 metres have received in-principle approval. Final clearance from the Central Water Commission is expected by the end of November.
June 2027 Deadline:
With dam construction and canal connectivity moving forward, the government is pushing to meet its June 2027 target. Completing Polavaram would mark a major milestone for Andhra Pradesh’s irrigation infrastructure and fulfil a long-awaited dream of the state’s people.